Replace Transformer SS-849 & Panel CP
Fast-track replacement of a unit substation with stainless-steel equipment, executed within a single 8-hour scheduled outage.
Project Details
- Owner
- NASA
- Role
- Contractor
- Contract Value
- $408,000.00
- Status
- In progress
Project Overview
Overstreet is removing and replacing an existing unit substation at Kennedy Space Center. The cut-over is performed as a single 8-hour scheduled power outage, followed by furnishing, installing and maintaining a 200 kW generator and fuel tank on a 24-hour basis until project completion.
The scheduled performance period is 60 days, subject to final acceptance, on a fast-track construction schedule.
Scope Highlights
- New 300 kVA pad-mounted stainless-steel transformer
- New 15 kV stainless-steel sectionalizing cabinet
- New 800 A NEMA 4X stainless-steel panelboard and custom NEMA 4X stainless splice box
- New Camlock generator receptacle
- New 15 kV feeders and duct banks
- New digital demand & revenue meter, CTs, CPT, control wiring, communication-protocol programming and demand settings
Outcomes
- Entire cut-over performed within a single 8-hour scheduled outage
- 60-day scheduled performance period
More work like this
Feeder 5 Electrical Upgrades
Design-build modification of the existing 13.2 kV overhead distribution system on Fort Sill, improving the reliability and safety of the installation's electrical network.
Electrical Upgrades, Area B
Replaced a loop-fed 6.9 kV distribution system with a new 15 kV system and installed a new 100 MVA power transformer — across 60+ buildings.
Modifications to Electrical Distribution System
New Central Energy Plant for the Fort Knox hospital with two 2.5 MW 15 kV generators, paralleling switchgear and five miles of rebuilt overhead distribution.